Teesta III Hydro Project Running Energy Loss & Harming Environment

Teesta III hydro power project suffered an energy loss of over 1450 million units between June-September 2017.

Published: 
story-hero-img
i
Aa
Aa
Small
Aa
Medium
Aa
Large

Reports of the Ministry of Power (MOP) and the Central Electricity Authority (CEA) indicate that the 1200 MW Teesta stage III hydro power project suffered an energy loss of over 1450 million units during the period June-September 2017. The loss is accountable to the non-completion of the 400 kv dc transmission line of Teesta III from Sikkim to Kishanganj Bihar.

The mega hydro project was officially commissioned in February 2017.

But due to the non-completion of the transmission line, the daily loss of peaking power is as high as 200-300 MW. Loss of peaking power and generation in non-peak periods is in non-compliance of CEA directions and MOP policy to shift from base load to peaking for hydro stations, informed VK Gupta, spokesperson for the All India Power Engineers’ Federation (AIPEF)

It was also observed that in addition to 400-500 MW spillage loss at Teesta III due to transmission constraints, the Rangpo Siliguri line operating at high loading was incurring power loss of the order of 40 MW during the June-September 2017 period.