Digha-AIIMS Elevated Road Opens: Big Relief For Patna, North Bihar

With the new bridge in place, patients will be able to travel to AIIMS without getting stuck in traffic jams.

Published
India
3 min read
story-hero-img
i
Aa
Aa
Small
Aa
Medium
Aa
Large
Hindi Female

Bihar Chief Minister Nitish Kumar on Monday, 30 November, inaugurated the Digha-AIIMS elevated road, providing easier access to the medical institution to millions of people from Chhapra, Muzaffarpur, Vaishali as well as all northwestern districts of Bihar.

The opening of this flyover will also help reduce crippling traffic jams within Patna.

A Relief For Patients

In the absence of this flyover, lakhs of people from several districts of north Bihar had to face huge traffic jams in order to come to Patna for treatment at AIIMS. But now, there will be a significant reduction in traffic within the city and people will be able to comfortably reach AIIMS from any city of north Bihar.

ADVERTISEMENTREMOVE AD

The distance between Patna and Muzaffarpur is roughly 90 kilometers. Before the construction of this flyover, it used to take four to five hours for people to cover this distance. But now, people will save at least two hours of journey time.

Many a times, patients travelling from Muzaffarpur or Chhapra would succumb to their ailments because of traffic jams. The new flyover will provide relief in this regard as well.
With the new bridge in place, patients will be able to travel to AIIMS without getting stuck in traffic jams.
Chief Minister Nitish Kumar, inaugurating the flyover.
(Photo: Quint Hindi)

Shorter Travel Time

Similarly, Chhapra is located 60 km from Patna. Before the construction of this flyover, it would take at least 2 hours to reach AIIMS. People first had to get down from Digha Sonepur flyover and go to the city from there, but now the flyover will reach AIIMS directly, which will save a lot of time.

0
People of north Bihar and Patna have been been struggling for the last several years in their commute because of traffic jams, as the vehicles coming from north Bihar had to pass through the city.

It will now be easier for vehicles coming from JP Sethu to go to north Bihar and from north Bihar to places like Naubatpur, Aurangabad etc.

With the new bridge in place, patients will be able to travel to AIIMS without getting stuck in traffic jams.
Chief Minister Nitish Kumar waving at people after inauguration.
(Photo: Quint Hindi)
ADVERTISEMENTREMOVE AD

Construction Began in 2013 With Budget of 1,298 Cr

Project manager Shashi Ranjan, on being asked about the delayed construction of the flyover, said that there were a lot of obstacles in the construction of the 106-meter wide Road Over Bridge (RoB).

There were also some technical difficulties in the construction of the railway over bridge being built in Khagaul. There were some issues in getting approval from the railways, which led to the delay, he said.

Snapshot

Construction of this flyover started in 2013

Rs 1,298 crore were spent on construction

The length of this elevated road is 8.5 km

The flyover was constructed by Gammon India Ltd

Ranjan also said that talks are underway for extending the flyover, to connect it to Bailey Road by next year. If this happens, people of Patna city will be largely relieved from the increasing problem of traffic jams, he added.

(This piece was originally published in Quint Hindi and has been translated and republished with permission. Read the original story here.)

(At The Quint, we are answerable only to our audience. Play an active role in shaping our journalism by becoming a member. Because the truth is worth it.)

Read Latest News and Breaking News at The Quint, browse for more from news and india

Topics:  Nitish Kumar   Bihar   Patna 

Speaking truth to power requires allies like you.
Become a Member
3 months
12 months
12 months
Check Member Benefits
Read More
×
×